76.
Weimer v Ember Resources Inc. - 2024 ABLPRT 906633 - 2024-12-13
SRA - S36: Recovery of CompensationDirection to Pay
Weimer v Ember Resources Inc., 2024 ABLPRT 906633, RC2023.0904 LAND AND PROPERTY RIGHTS TRIBUNAL [...] Weimer v Ember Resources Inc., 2024 ABLPRT 906633 Date: 2024-12-13 File No: [...] Ember Resources Inc., Operator, - and - Larry Wayne Weimer, Applicant.
-
77.
Schultz v Ember Resources Inc - 2022 ABLPRT SR900348 - 2022-09-26
SRA - S36: Recovery of CompensationCosts
Ember Resources Inc. - and - Russell Dean Schultz Operator, Applicant. [...] [3] By letter dated May 26, 2021, the Tribunal issued a Notice of Proceedings to Ember Resources Inc. By letter dated July 22, 2021, Ember responded to sixty Tribunal notices, including this Site. [...] Ember Resources Inc. - and - Russell Dean Schultz Operator, Applicant.
-
78.
Ember Resources Inc. v Kubinec - 2022 ABLPRT SR1278 - 2022-09-22
SRA - S29: Review of Decision/OrderOperator Identification
Other
Ember Resources Inc. v Kubinec, 2022 ABLPRT SR1278, BR2022.0040 Citation: [...] Between: Ember Resources Inc. Applicant, - and- Before: Patrick Joseph Kubinec [...] This Panel concludes that EMBER has established an unfair process. [17] EMBER has also established a mistake of fact in that payment for 2019 has been made.
-
79.
Bennett v Ember Resources Inc - 2023 ABLPRT SR900320 - 2023-07-11
SRA - S36: Recovery of CompensationOperator Identification
Bennett v Ember Resources Inc., 2023 ABLPRT 900320 Date: 2023-07-11 File No: [...] Ember Resources Inc., Operator, - and - Dennis W Bennett and Sylvia Sawyer, [...] As per the Panel, the offer letter by Ember Resources Inc. dated November 19, 2020, does not constitute a valid contract between the Applicants and Ember Resources Inc.
-
80.
McNair v Ember Resources Inc. - 2024 ABLPRT 903695 - 2024-07-30
SRA - S36: Recovery of CompensationDirection to Pay
McNair v Ember Resources Inc., 2024 ABLPRT 903695, RC2020.0170 Citation: Date: File No: Order No.: Municipality: [...] Ember Resources Inc., and Trident Exploration (Alberta) Corp., - and - [...] Subsequently, Ember Resources Inc. advised that they had paid the Applicant the sum of $1,332.43 on May 5, 2020.
-
81.
Poffenroth v Ember Resources Inc - 2023 ABLPRT 904641 - 2023-07-18
SRA - S36: Recovery of CompensationDirection to Pay
Poffenroth v Ember Resources Inc, 2023 ABLPRT 904641, RC2019.1563 Citation: Date: File No.: Order No.: Municipality: [...] [3] By letter dated December 7, 2022, the Tribunal issued a Notice and Demand for Payment to Ember Resources Inc. By letter dated March 14, 2023, the Tribunal issued a Notice and Demand for Payment to Ember Resources Inc. (Ember) and Trident Exploration (Alberta) Corp. [...] AER Licence No. 61430, Segment No. 12 for the Site is in the name of Ember. The Panel finds that Ember is an operator under section 36(1)(c) on the Right of Way 2019 due date.
-
82.
Ember Resources Inc. v Buckland - 2021 ABLPRT SR846 - 2021-12-13
SRA - S29: Review of Decision/OrderDismissed
Ember Resources Inc. v Buckland, 2021 ABLPRT 846 Date: 2021-12-13 File No. [...] Ember Resources Inc. Applicant/Operator, - and - Donald Ralph Buckland [...] We are counsel for Ember Resources Inc. (“Ember”) who is an operator in respect to the above matters.
-
83.
Ember Resources Inc. v Haller - 2021 ABLPRT SR864 - 2021-12-13
SRA - S29: Review of Decision/OrderDismissed
Ember Resources Inc. v Haller, 2021 ABLPRT 864 Date: 2021-12-13 File No. [...] Ember Resources Inc. Applicant/Operator, - and - Kevin Wade Haller [...] We are counsel for Ember Resources Inc. (“Ember”) who is an operator in respect to the above matters.
-
84.
Shirreff v Ember Resources Inc - 2022 ABLPRT SR900548 - 2022-11-21
SRA - S36: Recovery of CompensationOperator Identification
Shirreff v Ember Resources Inc, 2022 ABLPRT 900548 Date: 2022-11-21 File No.: [...] Ember Resources Inc. and HESC Energy Corporation Operators, - and - [...] [2] On July 16, 2021 Notice and Demand for Payment was sent to Ember Resources Inc. Ember Resources Inc. responded with a submission on September 16, 2021.
-
85.
Kaechele v Ember Resources Inc - 2022 ABLPRT SR1007 - 2022-07-12
SRA - S36: Recovery of CompensationOther
Kaechele v Ember Resources Inc, 2022 ABLPRT SR1007, RC2020.2320 LAND AND PROPERTY RIGHTS TRIBUNAL [...] Kaechele v Ember Resources Inc., 2022 ABLPRT 1007 Date: 2022-07-12 File No. RC2020.2320 [...] AER Well Licence No. 0334660 for the Site is in the name of Ember Resources Inc. The Panel finds that Ember Resources Inc. is an operator under section 36(1)(c) on the May 28, 2020, due date.
-
86.
Metzger v Ember Resources Inc - 2022 ABLPRT SR1009 - 2022-07-12
SRA - S36: Recovery of CompensationOperator Identification
Metzger v Ember Resources Inc, 2022 ABLPRT SR1009, RC2020.2099 LAND AND PROPERTY RIGHTS TRIBUNAL [...] Metzger v Ember Resources Inc., 2022 ABLPRT 1009 Date: 2022-07-12 File No. RC2020.2099 [...] Ember Resources Inc. and Bumper Development Corporation Ltd., Operators,
-
87.
Sandau v Ember Resources Inc. - 2022 ABLPRT SR570 - 2022-05-03
SRA - S36: Recovery of CompensationOperator Identification
Sandau v Ember Resources Inc., 2022 ABLPRT SR570, RC2020.0014 LAND AND PROPERTY RIGHTS TRIBUNAL [...] Ember Resources Inc. Operator, - and - Sandau Farms Ltd. Applicant. [...] AER Well License No. W0327689 for the Site is in the name of Ember Resources Inc. (“Ember”). The Panel finds that Ember is an operator under section 36(1)(c) on the January 6th, 2020 and January 6th, 2021 due dates.
-
88.
Tees v Ember Resources Inc - 2023 ABLPRT SR900081 - 2023-03-20
SRA - S36: Recovery of CompensationTermination
Tees v Ember Resources Inc, 2023 ABLPRT SR900081, RC2020.1648 LAND AND PROPERTY RIGHTS TRIBUNAL [...] Tees v Ember Resources Inc., 2023 ABLPRT 900081 Date: 2023-03-20 File No.: [...] Ember Resources Inc. Operator, - and - Matthew Philip Tees and Ronda Mae Tees
-
89.
Baerg v Ember Resources Inc - 2023 ABLPRT SR900402 - 2023-08-16
SRA - S36: Recovery of CompensationOperator Identification
Baerg v Ember Resources Inc, 2023 ABLPRT SR900402, RC2021.0713 LAND AND PROPERTY RIGHTS TRIBUNAL [...] Ember Resources Inc. and Bumper Development Corporation Ltd., Operators, [...] The licence for the Site is in the name of Ember Resources Inc. (“Ember”) as of September 3, 2010. The Panel finds that Ember is an Operator under section 36(1)(c) for 2020.
-
90.
Parker v Ember Resources Inc. - 2024 ABLPRT 905642 - 2024-10-24
SRA - S36: Recovery of CompensationDirection to Pay
Parker v Ember Resources Inc., 2024 ABLPRT 905642, RCR2024.1715 LAND AND PROPERTY RIGHTS TRIBUNAL [...] Parker v Ember Resources Inc., 2024 ABLPRT 905642 Date: 2024-10-24 File No: [...] Ember Resources Inc.: No written submission DIRECTION TO PAY PURSUANT TO
-
91.
Christie v Ember Resources Inc - 2024 ABLPRT 903756 - 2024-07-31
SRA - S36: Recovery of CompensationCompensation
Christie v Ember Resources Inc, 2024 ABLPRT 903756, RC2021.2289 Citation: Date: File No: Order No.: Municipality: [...] Ember Resources Inc., - and - James Panton Christie and Doris June Christie, [...] For the purposes of section 36 of the Act, the Operator is Ember Resources Inc. (“Ember”). The written evidence proves compensation in the amount of $2,392.00 is payable to the Applicant by the Operator.
-
92.
Balderson v Ember Resources Inc - 2022 ABLPRT SR1010 - 2022-07-12
SRA - S36: Recovery of CompensationDirection to Pay
Balderson v Ember Resources Inc, 2022 ABLPRT SR1010, RC2020.1619 LAND AND PROPERTY RIGHTS TRIBUNAL [...] Balderson v Ember Resources Inc, 2022 ABLPRT 1010 Date: 2022-07-12 File No.: RC2020.1619 [...] Ember Resources Inc. Operator, - and - Wayne Charles Balderson and
-
93.
Mantie v Ember Resources Inc., - 2024 ABLPRT 904668 - 2024-09-06
SRA - S36: Recovery of CompensationDirection to Pay
Mantie v Ember Resources Inc.,, 2024 ABLPRT 904668, RC2022.0080 Citation: Date: File No.: Order No.: Municipality: [...] Ember Resources Inc., - and - Brenda L Mantie, Romeo A. Rojas (“the Panel”) [...] [2] On July 7, 2023, the Applicant advised the Tribunal that it had received a payment of $600.00 from Ember Resources Inc. (“Ember”), in satisfaction of the Applicant’s claims for 2022 and 2023.
-
94.
Alberta Conservation Association v Ember Resources - 2024 ABLPRT 496 - 2024-09-27
SRA - S29: Review of Decision/OrderCompensation
Defunct or no operator
Direction to Pay
[5] Records obtained from the Alberta Energy Regulator (AER) named Ember Resources Inc. (EMBER) as the current Licensee. On that basis, on December 17, 2020 a Notice and Demand for Payment was issued to EMBER seeking payment of $1,550.00 for 2019. [...] [9] On February 22, 2021, Counsel for EMBER contacted the Tribunal regarding the Notice and Demand for Payment to indicate that EMBER had made full payment: [...] This is an active site; EMBER is an active corporation. EMBER has already paid costs in connection with an application that was subsequently abandoned.
-
95.
Toews v Ember Resources Inc. - 2024 ABLPRT 902356 - 2024-06-13
SRA - S36: Recovery of CompensationDirection to Pay
Toews v Ember Resources Inc., 2024 ABLPRT 902356, RC2023.0619 LAND AND PROPERTY RIGHTS TRIBUNAL [...] Toews v Ember Resources Inc., 2024 ABLPRT 902356 Date: 2024-06-13 File No: [...] Ember Resources Inc., Operator, - and - Harvey M Toews and Susan Joyce Toews,
-
96.
Vasseur v Ember Resources Inc. - 2022 ABLPRT SR900594 - 2022-12-20
SRA - S36: Recovery of CompensationDismissed
Vasseur v Ember Resources Inc., 2022 ABLPRT SR900594, RC2021.0112 Citation: LAND AND PROPERTY RIGHTS TRIBUNAL Vasseur v Ember Resources Inc, 2022 ABLPRT 900594 [...] For Ember Resources Inc.: ISSUES Decision No. LPRT2022/SR900594 Thomas R. Owen, Counsel, Owen Law Doug Dafoe, President, and CEO Ember Resources Inc.] [...] [4] Notice of Proceeding was sent to Bonavista Energy Corporation and Ember Resources Inc. (“Ember”) on January 28, 2021. Ember responded on February 17, 2022 by making the 2020 and 2021 payments.
-
97.
Ember Resources Inc. v Weigum - 2022 ABLPRT SR884 - 2022-06-17
SRA - S27: Review of CompensationEstablishing Rate of Compensation
Other
Ember Resources Inc. v Weigum, 2022 ABLPRT SR884, SL2021.0417 LAND AND PROPERTY RIGHTS TRIBUNAL [...] Weigum v Ember Resources Inc., 2025 ABLPRT 884 Date: 2022-06-17 File No. SL2021.0417 and SL2021.0418 [...] EMBER RESOURCES INC., Operator, Before: Susan McRory, Chair (the “Panel”)
-
98.
De Beaudrap v Ember Resources Inc - 2025 ABLPRT 900143 - 2025-01-09
SRA - S36: Recovery of CompensationDirection to Pay
Ember Resources Inc., Operators, -and- Jacques Louis De Beaudrap and [...] It is now apparent that a partial payment made by Ember Resources Inc. (EMBER) was not reported to the Tribunal. As of October 21, 2024 there is a new owner: Brandi Jean Marie Rosgen. [...] EMBER has not done so. EMBER, as a sophisticated operator, would be aware of the changes in the law and has chosen not to provide documentation in support of its position.
-
99.
Ember Resources Inc. v Anhorn - 2022 ABLPRT SR425 - 2022-03-09
SRA - S27: Review of CompensationEstablishing Rate of Compensation
Other
Ember Resources Inc. v Anhorn, 2022 ABLPRT SR425, SL2021.0369 LAND AND PROPERTY RIGHTS TRIBUNAL [...] EMBER RESOURCES INC., Operator Before: Susan McRory, Chair (the “Panel”) [...] Instead he suggests that an adjournment might “further appease Ember” and that “Ember may not be fully prepared”. [19] The DRC process relies upon accurate information being provided.
-
100.
De Beaudrap v Ember Resources Inc - 2025 ABLPRT 902876 - 2025-05-26
SRA - S36: Recovery of Compensation - YesCompensation
Ember Resources Inc., Operators, -and- Jacques Louis De Beaudrap and [...] 3. Ember Resources Inc.’s right to enter the site is suspended immediately. [...] Proper Notice was provided to EMBER, but EMBER did not make full payment. Accordingly, this Panel suspends EMBER’s right to enter the site immediately.